Update, August 5, 2022

Remedial Investigation Commences

Remedial Investigation

Remedial Investigation field work at the former Williamsburg Works MGP is being conducted under a New York State Department of Environmental Conservation (NYSDEC)-approved Remedial Investigation Work Plan Addendum (RIWPA) for Parcels 3 and 4. The work includes the installation of soil borings, monitoring wells, test pits, and soil vapor points to gather information required to determine the nature and extent of impacts at Parcels 3 and 4 of the former Williamsburg Works MGP. The RIWPA field work began on July 7, 2022. Community air monitoring was initiated on Monday, July 11, 2022, and will continue during intrusive activities on Site.

Website Updates:

On-going activities:

  • Continued soil boring and monitoring well installation activities on-Site and on N. 12th Street.

Recently Completed:

  • Completed mobilization activities; and
  • Completed utility mark outs.

Upcoming activities:

  • Continue soil boring and monitoring well installation activities on-Site and on N. 12th Street.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 982-7349.

Photos of Activity


Photo 1: View facing northeast of soil boring drilling activities.


Photo 2: View facing northeast of hand clearing activities.