williamsburg
About the Williamsburg former Manufactured Gas Plant Site

header

Gas used for cooking, lighting, heating and commercial purposes was manufactured at the Williamsburg Manufactured Gas Plant (MGP) from approximately 1887 through the late 1930’s or early 1940’s. Historical records, while incomplete, indicate that an independent company operated the plant before that company merged to form Brooklyn Union Gas in 1895. The plant used coal and petroleum products to create a flammable gas which was piped into the surrounding neighborhoods. After the property was sold by Brooklyn Union, it was subdivided and now has multiple private owners and uses, including commercial and warehouse operations and a former City of New York Department of Sanitation garage. National Grid is responsible for the investigation and remediation of the site because it was operated by a predecessor company (Brooklyn Union) at the time MGP-related contamination occurred.

This website provides information on the Williamsburg former MGP Site, the Remedial Investigation of the site, and opportunities for public participation. National Grid is committed to the protection and enhancement of the environment, always seeking ways to minimize the environmental impacts of our past, present and future activities. We hope this website, a part of our public participation and outreach efforts, is helpful and informative. If you need additional information or have suggestions to make our website better, please contact the individuals listed under Contacts.

For more information about the New York State Department of Environmental Conservation’s Manufactured Gas Plant Site program go to: http://www.dec.ny.gov/
chemical/8430.html

Site News and Updates

August 2024

Supplemental Remedial Investigation Commences

Supplemental Remedial Investigation (SRI)

Supplemental Remedial Investigation (SRI) field work will be conducted at the former Williamsburg Works MGP site under a New York State Department of Environmental Conservation (NYSDEC) approved SRI Work Plan. The purpose of the work is to delineate vertical groundwater at Parcels 3 and 4 of the site.

The work consists of installation and development of 16 monitoring wells on Parcels 3 and 4. The wells will then be left to equilibrate for two weeks prior to sampling. The work will begin in August and is expected to be completed by the end of September.

A map of the site and parcels can be seen on the Site Description tab.

Ongoing Activities:

  • Preparation for mobilization and fieldwork

Upcoming Activities:

  • Conduct approved Supplemental Remedial Investigation
  • Mobilization, installation of fencing, and pre-clearing activities will take place

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 982-7349.