Update for the Week Ending January 15, 2016

Site Mobilization Continues

On-going activities:

  • Continued mobilization of equipment and supplies;
  • Continued winterization activities for the Water Treatment Plant (WTP);
  • Continued the assembly of the Temporary Containment Building (TCB) base frame;
  • Continued the assembly of the grout plant;
  • Continued the installation of Site electrical service for the WTP and TCB vapor management system (VMS);
  • Installing the decontamination pad for washing trucks and equipment that will exit the Site;
  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor suppressant foam as needed for dust and odor control; and
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site).

Recently completed activities:

  • Conducted a small, shallow preclearance test pit to inspect the outer edge of the Holder No. 2 tank and collected soil samples for the preparation of grout/soil mix cylinders to be tested for strength and permeability prior to beginning the bucket soil mixing (BSM).

Upcoming activities:

  • Decommission former monitoring wells within the excavation area;
  • Assemble the TCB superstructure over the Holder No. 2 tank and install the VMS;
  • Commission the grout plant and conduct the BSM demonstration test in the Holder No. 2 tank;
  • Conduct a Level A subsurface survey in Kent Avenue;
  • Install the WTP treated water discharge line beneath Kent Avenue to tie into the NYCDEP sewer line;
  • Install electrical service from Con Edison and demobilize the temporary generator from the Site; and
  • Install dewatering wells, initiate ground water extraction, and begin operation of the WTP.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted. 

There were no fifteen-minute Action Level exceedances of Total Volatile Organic Compounds (TVOCs) or odors associated with Site activities during this reporting period.

A fifteen-minute Action Level exceedance for particulate matter (PM-10) [average dust concentration] occurred on January 12, 2016 at air monitoring station 3 (AMS-3) from 9:22 a.m. to 9:33 a.m.  This exceedance was due to dust from breaking clean asphalt and concrete in preparation for excavating a test pit over the Holder No. 2 tank.  Odor/dust suppressant foam was applied to the area, and dust levels returned to below the Action Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Winterizing water treatment plant components

Layout and assembly of the temporary containment building (TCB) base frame over the Holder No. 2 tank

Assembling the TCB base frame

Mobilizing the TCB superstructure frame and components

Assembling the TCB superstructure frame

Assembling the TCB superstructure frame

Conduits installed for electrical service on Site

 

Update for the Week Ending January 29, 2016

Site Mobilization Continues

On-going activities:

  • Initiated installation of the vapor management system (VMS) components;
  • Initiated start-up and testing of the water treatment plant (WTP);
  • Continued mobilization of equipment and supplies;
  • Continued fabrication of the Temporary Containment Building (TCB) base frame;
  • Continued the assembly of the TCB superstructure (frame and fabric);
  • Continued the installation of Site electrical service for the water treatment plant (WTP), TCB and TCB vapor management system (VMS);
  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor suppressant foam as needed for dust and odor control; and
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site).

Recently completed activities:

  • Installed the decontamination pad for washing trucks and equipment as they exit the Site.

Upcoming activities:

  • Ship impacted shallow soils for treatment and disposal;
  • Ship removed asphalt for recycling;
  • Decommission former monitoring wells on Site;
  • Conduct the bucket soil mixing (BSM) demonstration test in the Holder No. 2 tank within the TCB;
  • Install the WTP treated water discharge line beneath Kent Avenue to tie into the NYCDEP sewer line;
  • Install electrical service from Con Edison and demobilize the temporary generator from the Site; and
  • Install dewatering wells, initiate ground water extraction, and begin operation of the WTP.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted. 

There were no fifteen-minute Action Limit exceedances of Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors associated with Site activities during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Installation of the decontamination pad for washing trucks and equipment prior to exiting the Site

Installing fabric on the eastern gable end of the TCB

Installing fabric on the western gable end of the TCB

Installing a stone ramp at the northern side truck entrance of the TCB

Loading carbon into the adsorbers for the TCB vapor management system

 

Update for the Week Ending February 5, 2016

Site Mobilization Continues

On-going activities:

  • Continued mobilization of equipment and supplies;
  • Continued the installation of Site electrical service for the water treatment plant (WTP), TCB, and TCB vapor management system (VMS);
  • Continued installation of the VMS components;
  • Continued start-up and testing of the WTP;
  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor suppressant foam as needed for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site);
  • Initiated the removal of hardscape (asphalt and concrete) over the Holder No. 2 tank ; and
  • Initiated the excavation of shallow soils within the Holder No. 2 tank beneath the TCB in preparation for the bucket soil mixing (BSM) demonstration test.

Recently completed activities:

  • Completed fabrication of the Temporary Containment Building (TCB) base frame;
  • Completed the assembly of the TCB superstructure (frame and fabric); and
  • Installed the WTP treated water discharge line beneath Kent Avenue to tie into the NYCDEP sewer line.

Upcoming activities:

  • Conduct the BSM demonstration test in the Holder No. 2 tank within the TCB;
  • Ship impacted shallow soils for treatment and disposal;
  • Ship removed asphalt for recycling;
  • Perform pre-trenching for on-Site utility clearance along the support of excavation (SOE) wall perimeter;
  • Decommission former monitoring wells on Site;
  • Install electrical service from Con Edison and demobilize the temporary generator from the Site; and
  • Install dewatering wells, initiate ground water extraction, and begin operation of the WTP.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted. 

There were no fifteen-minute Action Limit exceedances of Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors associated with Site activities during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Completed the installation of the temporary containment building (TCB) superstructure (fabric and frame)

Continued installation of the vapor management system (VMS) for the TCB

Initiated the removal of hardscape (asphalt and concrete) over the Holder No. 2 tank within the TCB

Initiated shallow excavation inside the Holder No. 2 tank within the TCB

Installing soil and silt protection fabric in the storm water catch basin prior to initiating excavation for the sewer tie-in within Kent Avenue

Installing the WTP discharge line and tie-in to the NYCDEP sewer beneath Kent Avenue

Installing the WTP discharge line and tie-in to the NYCDEP sewer beneath Kent Avenue

 

Update for the Week Ending February 12, 2016

Site Mobilization Completed
Site Remediation Begins

On-going activities:

  • Continued the installation of Site electrical service for the water treatment plant (WTP), TCB, and TCB vapor management system (VMS);
  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam as needed for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site);
  • Continued the removal of hardscape (asphalt and concrete) over the Holder No. 2 tank;
  • Continued the excavation of shallow soils within the Holder No. 2 tank beneath the TCB in preparation for the bucket soil mixing (BSM) demonstration test;
  • Initiated operation of the WTP;
  • Initiated truck lining, loading, and shipment of impacted soils to Bayshore Soil Management for treatment and disposal:
  • 12 trucks: 322.06 tons shipped last week; and
  • 322.06 tons shipped to date.
  • Initiated the BSM demonstration test.

Recently completed activities:

  • Completed mobilization of equipment and supplies;
  • Completed installation of the VMS components; and
  • Completed start-up and testing of the WTP.

Upcoming activities:

  • Complete the BSM demonstration test in the Holder No. 2 tank within the TCB;
  • Conduct full scale BSM in the Holder No. 2 tank;
  • Continue the shipment of impacted shallow soils for treatment and disposal;
  • Ship removed asphalt for recycling;
  • Perform pre-trenching for on-Site utility clearance along the support of excavation (SOE) wall perimeter;
  • Decommission former monitoring wells on Site;
  • Install electrical service from Con Edison and demobilize the temporary generator from the Site; and
  • Install dewatering wells, initiate ground water extraction, and begin operation of the WTP.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances of Total Volatile Organic (TVOCs) or odors during this reporting period.

There were six instances of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] on February 11, 2016, exceeding the applicable Action Limit during windy conditions.  These concentrations are attributed to clean fill.  Work was stopped repeatedly and water and calcium chloride were applied until dust levels returned to below the response limit and Site work resumed.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Continuing the excavation of shallow soils in the Holder No. 2 tank within the temporary containment building (TCB)

Continuing the excavation of shallow soils in the Holder No. 2 tank in the TCB

Continuing the transfer of reusable soil to the on-Site stockpile

Excavating material from the Holder No. 2 tank in preparation for the Bucket Soil Mix (BSM) demonstration test

Initiating the BSM demonstration test in the Holder No. 2 tank within the TCB

Loading the lined trucks with impacted soil for shipment to Bayshore Soil Management for treatment and disposal

Cleaning trucks on the decontamination pad prior to leaving the Site on N. 11th Avenue


Update for the Week Ending February 19, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the WTP;
  • Continued the Bucket Soil Mixing (BSM) demonstration test in the Holder No. 2 tank beneath the temporary containment building (TCB); and
  • Initiated pre-trenching and demolition of subsurface obstructions in the alignment of the Support of Excavation (SOE) wall.

Recently completed activities:

  • Completed the removal of asphalt along the SOE wall alignment in preparation for pre-trenching.

Upcoming activities:

  • Conduct full scale BSM in the Holder No. 2 tank;
  • Continue the shipment of impacted shallow soils for treatment and disposal;
  • Ship removed asphalt for recycling;
  • Decommission former monitoring wells on Site;
  • Pre-drill for deep obstruction removal along the SOE wall alignment;
  • Crush clean, reusable concrete for use as backfill in the deep excavation;
  • Install electrical service from Con Edison and demobilize the temporary generator from the Site; and
  • Install dewatering wells and initiate ground water extraction.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances of Total Volatile Organic (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on February 15, 2016, attributable to offloading a delivery of cement to the storage silo at the on Site grout plant.  Following the offloading, dust levels returned to below the Response Limit.  A shield will be installed over the silo relief port, and a water atomizing mister will be utilized to mitigate dust from the grout plant operations.

There was one instance of the fifteen-minute average concentration of PM-10 [dust] and one instance of odor exceeding the applicable Action Limit on February 18, 2016, attributable to pre-trenching activities.  Work was stopped, and water (with BioSolve) and odor suppressant foam were applied to the pre-trenching area until dust and odor levels returned to below the Response and Action Limits, respectively.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Removing asphalt along the SOE wall alignment in preparation for pre-trenching

Removing asphalt along the SOE wall alignment in preparation for pre-trenching

Initiating pretrenching along the SOE wall aligment and applying water with BioSolve for dust and odor control

Pre-trenching along the SOE wall alignment and applying odor suppressant foam for dust and odor control

Pumping water from the Holder No. 2 tank for transfer to the water treatment plant prior to conducting bucket soil mixing

Conducting the bucket soil mixing demonstration test in the Holder No, 2 tank beneath the temporary containment building

Covering the reuse soil stockpile with heavy duty tarps for dust control

 

Update for the Week Ending February 26, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the WTP; and
  • Continued pre-trenching and demolition of subsurface obstructions in the alignment of the Support of Excavation (SOE) wall.

Upcoming activities:

  • Conduct full scale Bucket Soil Mixing (BSM) in the Holder No. 2 tank;
  • Continue the shipment of impacted shallow soils for treatment and disposal;
  • Ship removed asphalt for recycling;
  • Pre-drill for deep obstruction removal along the SOE wall alignment;
  • Crush clean, reusable concrete for use as backfill in the deep excavation;
  • Install electrical service from Con Edison and demobilize the temporary generator from the Site; and
  • Install dewatering wells and initiate ground water extraction.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances of Total Volatile Organics (TVOCs) or odors during this reporting period.

There was one period of the fifteen-minute average concentrations of Particulate Matter (PM-10) [dust] exceeding the Action Limit on Sunday, February 28, 2016, when no Site activities were being conducted.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Pre-trenching along the SOE wall alignment for the removal of shallow subsurface obstructions. Applying water with BioSolve to mitigate dust and odors.

Pre-trenching along the SOE wall alignment for the removal of shallow subsurface obstructions. Applying odor suppressant foam and water to mitigate VOCs, dust and odors.

Using non-mechanical procedures (vacuum truck) to identify utilities prior to pre-trenching along the SOE wall alignment.

Sizing concrete obstructions removed during pre-trenching along the SOE wall alignment.



Update for the Week Ending March 4, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the WTP;
  • Continued pre-trenching and demolition of subsurface obstructions in the alignment of the Support of Excavation (SOE) wall; and
  • Continued the lining, loading, and shipment of impacted soils to Bayshore Soil Management for treatment and disposal:
    • 18 trucks; 497.17 tons shipped last week; and
    • 819.23 tons shipped to date.

Recently completed activities:

  • Core drilled the Bucket Soil Mix (BSM) In-Situ Stabilization (ISS) demonstration test area and verified that the BSM successfully solidified the material in the Holder No. 2 tank as verified by the Engineer and NYSDEC; and
  • Installed electrical service from Con Edison to the Site and demobilized the temporary generator.

Upcoming activities:

  • Conduct full scale Bucket Soil Mixing (BSM) in the Holder No. 2 tank;
  • Ship removed asphalt for recycling;
  • Pre-drill for deep obstruction removal along the SOE wall alignment;
  • Crush clean, reusable concrete for use as backfill in the deep excavation; and
  • Install dewatering wells and initiate ground water extraction.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances of Total Volatile Organics (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentrations of Particulate Matter (PM-10) [dust] exceeding the Action Limit on Friday, March 4, 2016, during the delivery of clean slag/cement to the grout plant.  Once the slag/cement was off-loaded from the tanker delivery truck to the Site storage silo, the dust concentration returned to below the Response Limit.  Plastic sheeting will be placed over the delivery truck relief port with future deliveries to mitigate the dust.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity

Pre-trenching along the SOE wall alignment for the removal of shallow subsurface obstructions.

Loading the lined trucks for shipment of impacted soils to Bayshore Soil Management for treatment and disposal

Cleaning (pressure washing) the trucks on the decontamination pad prior to leaving the Site on North 11th Street

Core drilling the BSM demonstration test area to verify the successful solidification of the material in the Holder No. 2 tank.

Con Edison pulling wire for the electrical service connection to the Site.

Demobilizing the temporary generator from the Site.



Update for the Week Ending March 11, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the WTP;
  • Continued pre-trenching and demolition of subsurface obstructions in the alignment of the Support of Excavation (SOE) wall;
  • Continued the lining, loading, and shipment of impacted soils to Bayshore Soil Management for treatment and disposal:
  • Initiated full scale Bucket Soil Mixing (BSM) In-Situ Stabilization (ISS) in the Holder No. 2 tank; and
  • Mobilized a drill rig and initiated pre-drilling for deep obstruction identification and removal along the alignment of the SOE wall.

Recently completed activities:

  • Completed the ISS BSM stabilization of five of twenty cells (six of twenty completed to date) in the Holder No. 2 tank; and
  • Lined, loaded, and shipped trucks of impacted soils to Bayshore Soil Management and Clean Earth of North Jersey for treatment and disposal:
    • 17 trucks; 445.92 tons shipped last week; and
    • 1,265.15 tons shipped to date.

Upcoming activities:

  • Ship removed asphalt for recycling;
  • Crush clean, reusable concrete for use as backfill in the deep excavation; and
  • Install dewatering wells and initiate deep ground water extraction.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances of Total Volatile Organics (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentrations of Particulate Matter (PM-10) [dust] exceeding the Action Limit on Friday, March 4, 2016, during the delivery of clean slag/cement to the grout plant.  Once the slag/cement was off-loaded from the tanker delivery truck to the Site storage silo, the dust concentration returned to below the Response Limit.  Plastic sheeting will be placed over the delivery truck relief port with future deliveries to mitigate the dust.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Pre-trenching along the SOE wall alignment for the removal of shallow subsurface obstructions.


Pre-drilling for deep obstruction identification and removal along the SOE wall alignment.


Pre-drilling and pre-trenching for obstruction removal along the SOE wall alignment.


Loading lined trucks with impacted material for shipment to Clean Earth of North Jersey for treatment and disposal.


ISS BSM in the Holder No. 2 tank beneath the Temporary Containment Building (TCB).


Off-loading cement at the on Site grout plant silo for the ISS BSM.


Applying odor-suppressant foam to impacted material for odor control.


Pressure washing truck tires on the decontamination pad prior to exiting the Site onto North 11th Street.



Update for the Week Ending March 25, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued the full scale In-Situ Stabilization (ISS) Bucket Soil Mixing (BSM) in the Holder No. 2 tank;
  • Continued pre-drilling for deep obstruction identification and removal along the alignment of the SOE wall;
  • Continued crushing clean, reusable concrete and soil for use as backfill in the deep excavation; and
  • Continued the lining, loading, and shipment of trucks of impacted soils to Bayshore Soil Management for treatment and disposal:
    • 6 trucks; 157.17 tons shipped last week; and
    • 1,422.32 tons shipped to date.

Recently completed activities:

  • Completed the ISS BSM stabilization of four cells in the Holder No. 2 tank. Fifteen of twenty cells have been stabilized to date.

Upcoming activities:

  • Conduct a demonstration test for sheet pile installation for the support of excavation (SOE) wall for the deep excavation;
  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal;
  • Ship removed asphalt for recycling; and
  • Install dewatering wells and initiate deep ground water extraction.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on March 23, 2016, due to dust from the rock crusher.  Additional water was applied during crushing, and the dust levels decreased below the Action Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Stockpiling crushed rock and other material to use as backfill for the deep excavation area.


Applying water for dust control during rock crushing activities.


Loading lined trucks for the shipment of impacted material to Bayshore Soil Management for treatment and disposal.


Predrilling for deep obstruction identification along the SOE wall alignment.


Conducting ISS BSM in the Holder No. 2 tank beneath the temporary containment building (TCB).


Applying odor suppression foam during the ISS BSM to control odors and TVOCs.


Installing a second truck entrance door on the TCB to control odors.



Update for the Week Ending April 1, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued the full scale In-Situ Stabilization (ISS) Bucket Soil Mixing (BSM) in the Holder No. 2 tank;
  • Continued pre-drilling for deep obstruction identification and removal along the alignment of the support of excavation (SOE) wall;
  • Continued crushing reusable concrete and soil for backfill in the deep excavation; and
  • Continued the lining, loading, and shipment of trucks of impacted soils to Bayshore Soil Management for treatment and disposal:
    • 14 trucks; 346.67 tons shipped last week; and
    • 1,768.99 tons shipped to date.

Recently completed activities:

  • Completed the ISS BSM stabilization of five cells in the Holder No. 2 tank. Twenty of twenty cells have been stabilized to date.

Upcoming activities:

  • Complete the ISS in the Holder No. 2 tank with the stabilization, above the twenty stabilized cells, of the remaining, top material ;
  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal;
  • Ship removed asphalt for recycling; and
  • Complete pre-clearing and initiate the installation of the cement/bentonite slurry trench for installation of the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There were three instances of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit.  Dust was measured above the Action Limit of 150 µg/m3 at AMS-2 on March 28, 2016 caused by spraying water to clean the grout plant near AMS-2.  Dust was measured at the Action Limit of 150 µg/m3 at AMS-3 on March 31, 2016 and April 1, 2016 due to a rock crusher blowing small amounts of dust in the air.  Additional water was applied with a fire hose during crushing, and the dust levels decreased below the Action Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Crushing clean rock and reuse material and applying water for dust control.


Pre-drilling for deep obstruction identification along the SOE wall alignment.


Conducting ISS BSM in the Holder No. 2 tank beneath the temporary containment building (TCB).


Applying long duration foam to the reuse soil stockpiles for dust control.



Update for the Week Ending April 8, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued pre-drilling for deep obstruction identification and removal along the alignment of the support of excavation (SOE) wall;
  • Initiated the backfilling of the Holder No. 2 tank with reuse material for future placement in the deep excavation; and
  • Loaded and shipped clean asphalt to Bayshore Soil Management for recycling:
    • 10 trucks; 253.32 tons shipped last week; and
    • 253.32 tons shipped to Bayshore to date.

Recently completed activities:

  • Completed the full scale In-Situ Stabilization (ISS) Bucket Soil Mixing (BSM) in the Holder No. 2 tank with the stabilization of the remaining, top material in the Holder No. 2 tank above the twenty stabilized cells; and
  • Completed crushing clean, reusable concrete and soil for use as backfill in the deep excavation.

Upcoming activities:

  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal; and
  • Complete pre-clearing and initiate the excavation of the cement/bentonite slurry (CB) trench for installation of the SOE wall sheet piles.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Pre-drilling for deep obstruction identification along the eastern alignment of the SOE wall.


Completing the final, top layer of the ISS BSM in the Holder No. 2 tank beneath the temporary containment building (TCB).


Placing backfill in the Holder No. 2 tank above the ISS material beneath the TCB.


Grading backfill placed above the ISS in the Holder No. 2 tank beneath the TCB.


Loading clean asphalt for shipment to Bayshore Soil Management for recycling.



Update for the Week Ending April 15, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for dust and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued investigatory pre-drilling for deep obstruction identification along the alignment of the support of excavation (SOE) wall; and
  • Initiated modification of the Temporary Containment Building (TCB) to remove the western-most (gable end) bay in preparation for excavating the cement/bentonite (CB) slurry trench along the east SOE alignment.

Recently completed activities:

  • Completed backfilling the Holder No. 2 tank with reuse material for future placement in the deep excavation.

Upcoming activities:

  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal; and
  • Initiate the excavation of the CB slurry trench for installation of the SOE wall sheet piles.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Investigatory pre-drilling for deep obstruction identification along the north alignment of the SOE wall.


Investigatory Pre-drilling for deep obstruction identification along the south alignment of the SOE wall.


Investigatory Pre-drilling for deep obstruction identification along the east alignment of the SOE wall.


Grading backfill placed above the ISS in the Holder No. 2 tank beneath the TCB.


Installing reinforcement to east end of the TCB in preparation for the removal of a western-most bay.



Update for the Week Ending April 22, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer; and
  • Continued investigatory pre-drilling for deep obstruction identification along the alignment of the support of excavation (SOE) wall.

Recently completed activities:

  • Completed modification of the Temporary Containment Building (TCB) to remove a western (gable end) bay in preparation for excavating the eastern alignment of the cement/bentonite (CB) slurry trench and installation of the SOE wall.

Upcoming activities:

  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal; and
  • Initiate the excavation of the CB slurry wall for installation of the SOE sheet piles.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Investigatory pre-drilling for deep obstruction identification along the southern alignment of the SOE wall.


Mobilizing a fractionation (storage) tank to the Site grout plant for bentonite hydration and mixing for the CB grout.


Removing a western bay of the TCB for the installation of the eastern alignment of the CB slurry wall and SOE .


Reinstalling fabric over the western gable end of the TCB.


Pressure washing truck tires at the decontamination pad prior to exiting the Site onto North 11th Street.



Update for the Week Ending April 29, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued investigatory pre-drilling for deep obstruction identification along the alignment of the support of excavation (SOE) wall;
  • Initiated the excavation of the cement/bentonite (CB) slurry wall for installation of the SOE sheet piles; and
  • Continued the lining, loading, and shipment of trucks of impacted material to Bayshore Soil Management for treatment and disposal:
  • 20 trucks; 521.09 tons shipped last week; and
  • 2,290.08 tons shipped to date

Recently completed activities:

  • Completed preparation of a lined containment area in the temporary containment building (TCB) for placement of the excavated spoils from the CB wall installation.

Upcoming activities:

  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal; and
  • Continue the excavation of the CB slurry trench for installation of the SOE wall sheet piles.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Mobilizing sheet piles to the Site for the SOE wall.


Conducting investigatory pre-drilling for deep obstruction identification along the southern alignment of the SOE wall.


Preparing a lined containment area in the TCB for the excavated CB slurry wall spoils.


Excavating the CB slurry wall along the eastern alignment of the SOE wall, while employing foam for odor control.


Loading excavated CB slurry wall spoils into a truck for transfer to the containment area in the TCB.


Sounding the CB slurry wall to verify depth to 48 feet below ground surface.


Installing sheet piles in the CB slurry wall.


Loading lined trucks with soil for shipment to Bayshore Soil Management for treatment and disposal.



Update for the Week Ending May 6, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer; and
  • Continued investigatory pre-drilling for deep obstruction identification along the alignment of the support of excavation (SOE) wall.

Upcoming activities:

  • Continue the lining, loading, and shipment of trucks of impacted soil to Bayshore Soil Management for treatment and disposal; and
  • Continue the excavation of the CB slurry trench for installation of the SOE wall sheet piles.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Mobilizing sheet piles to the Site for the SOE wall.


Conducting investigatory pre-drilling for deep obstruction identification along the eastern alignment of the SOE wall.


Conducting investigatory pre-drilling for deep obstruction identification along the eastern alignment of the SOE wall.

 

Update for the Week Ending May 13, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued investigatory pre-drilling for deep obstruction identification along the alignment of the support of excavation (SOE) wall;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 6 trucks; 198.32 tons shipped last week; and
    • 2,265.00 tons shipped to date.
  • Initiated excavation and installation of the cement/bentonite (CB) slurry trench for installation of the SOE wall sheet piles:
  • 63 linear feet installed last week; and
  • 63 of 620 linear feet installed to date

Upcoming activities:

  • Initiate installation of the SOE sheet piles in the CB slurry trench.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs), or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on May 11, 2016, due to dust created during cement and bentonite mixing at the grout plant.  Work was stopped, and the dust levels decreased below the Action Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Conducting investigatory pre-drilling for deep obstruction identification along the western alignment of the SOE wall.


Installing the CB slurry trench along the eastern SOE wall alignment.


Applying odor suppressant foam during installation of the CB slurry trench for odor control.


Installing the CB slurry trench along the eastern SOE wall alignment.


Loading soil removed from the CB slurry trench for transfer to the Temporary Containment Building (TCB).


Offloading soil removed from the CB slurry trench in the lined containment area in the TCB.


Pressure washing trucks on the decontamination pad prior to exiting the Site onto N. 11th Street.



Update for the Week Ending May 20, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 32 trucks; 894.60 tons shipped last week; and
    • 3,159.60 tons shipped to date.
  • Continued excavation and installation of the cement/bentonite (CB) slurry trench for installation of the SOE wall sheet piles:
  • 93 linear feet installed last week; and
  • 156 of 629 linear feet installed to date
  • Initiated the installation of the sheet piles in the CB slurry trench:
    • 41 linear feet installed last week; and
    • 41 of 629 linear feet installed to date.

Recently completed activities:

  • Completed investigatory predrilling for obstruction identification along the alignment of the SOE wall.

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Install deep wells for dewatering in preparation for conducting the deep excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on May 18, 2016, associated with welding being conducted adjacent to the air monitoring station.  The welding operation was relocated, and dust levels returned to below the Response Limit.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on May 20, 2016, associated with the transfer and loading of bentonite at the grout plant.  Work was stopped, and the bentonite bags were removed by laborers instead of the fork lift, and dust levels returned to below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Conducting investigatory pre-drilling for deep obstruction identification along the western alignment of the SOE wall.


Installing the CB slurry trench along the eastern SOE wall alignment.


Installing the CB slurry trench along the eastern SOE wall alignment.


Loading soil removed from the CB slurry trench for transfer to the lined containment area in the TCB.


Staging sheet piles in preparation for installation in the CB slurry trench.


Installing sheet piles in the CB slurry trench along the eastern alignment of the SOE wall.


Installing sheet piles in the CB slurry trench along the eastern alignment of the SOE wall.


Offloading cement at the grout plant for mixing grout for the CB slurry trench.



Update for the Week Ending May 27, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 31 trucks; 865.25 tons shipped last week; and
    • 4,024.85 tons shipped to date.
  • Continued excavation and installation of the cement/bentonite (CB) slurry trench for installation of the Support of Excavation (SOE) wall sheet piles:
  • 126 linear feet installed last week; and
  • 282 of 629 linear feet installed to date
  • Continued the installation of the sheet piles in the CB slurry trench:
    • 96.5 linear feet installed last week; and
    • 137.8 of 629 linear feet installed to date.

Recently completed activities:

  • Completed installation of the CB slurry trench along the south alignment of the SOE wall.

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Install deep wells for dewatering in preparation for conducting the deep excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There were two instances of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust], exceeding the applicable Action Limit on May 24, 2016, associated with offloading cement and mixing operations at the grout plant.  A plastic shroud and additional water spraying were deployed, and dust levels returned to below the Response Limit.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on May 20, 2016, associated with the transfer and loading of bentonite at the grout plant.  Work was stopped, and the bentonite bags were removed by laborers instead of the fork lift, and dust levels returned to below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing sheet piles in the CB slurry trench along the east alignment of the SOE wall.


Excavating deep obstruction during installation of the CB slurry trench along the east alignment of the SOE wall and applying odor control foam.


Excavating soil during installation of the CB slurry trench along the south alignment of the SOE wall.


Excavating and installing the CB slurry trench along the south alignment of the SOE wall.


Offloading excavated CB spoils in the lined containment area in the TCB.


Repairing tears to the fabric caused by wind on the western gable end of the TCB.


Applying foam to CB slurry trench spoils for odor and vapor control in the TCB.



Update for the Week Ending June 3, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 15 trucks; 427.20 tons shipped last week; and
    • 4,452.05 tons shipped to date.
  • Continued excavation and installation of the cement/bentonite (CB) slurry trench for installation of the support of excavation (SOE) wall sheet piles:
  • None installed to final depth (48 feet below ground surface); and
  • 282 of 629 linear feet installed to date

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Install deep wells for dewatering in preparation for conducting the deep excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Loading CB slurry spoils for transfer to the lined containment area in the TCB.


Closing the truck liner prior to proceeding to the decontamination pad.


Offloading super sacks of bentonite at the grout plant using a plastic shroud and water to mitigate dust.



Update for the Week Ending June 10, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 26 trucks; 675.27 tons shipped last week; and
    • 5,127.32 tons shipped to date.
  • Continued excavation and installation of the cement/bentonite (CB) slurry trench for installation of the support of excavation (SOE) wall sheet piles:
  • 131 linear feet installed last week; and
  • 413 of 629 linear feet installed to date.
  • Continued installation of the sheet piles in the CB slurry trench for the SOE wall:
    • 78.1 linear feet installed last week; and
    • 225 of 629 linear feet installed to date.

Recently completed activities:

  • Completed installation of the CB slurry trench along the east alignment of the SOE wall; and
  • Completed installation of sheet piles in the CB slurry trench along the east alignment of the SOE wall.

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Install deep wells for dewatering in preparation for conducting the deep excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Raising sheet piles in preparation for installation in the CB slurry trench along the east alignment of the SOE wall.


Installing sheet piles along the east alignment of the SOE wall.


Installing sheet piles along the south alignment of the SOE wall.


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Washing stone delivery trucks on the decontamination pad prior to exiting the Site.



Update for the Week Ending June 17, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 41 trucks; 1,185.59 tons shipped last week; and
    • 6,312.91 tons shipped to date.
  • Continued excavation and installation of the cement/bentonite (CB) slurry trench for installation of the support of excavation (SOE) wall sheet piles:
  • 169 linear feet installed last week; and
  • 582 of 629 linear feet installed to date.
  • Continued installation of the sheet piles in the CB slurry trench for the SOE wall:
    • 142.3 linear feet installed last week; and
    • 367.2 of 629 linear feet installed to date.

Recently completed activities:

  • Completed installation of the CB slurry trench along the west alignment of the SOE wall; and
  • Completed installation of sheet piles in the CB slurry trench along the south alignment of the SOE wall.

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Initiate abandonment of monitoring wells located within the excavation;
  • Install deep wells for dewatering in preparation for conducting the deep excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on June 14, 2016, due to dust generated during mixing at the grout plant.  Additional water was sprayed during mixing, and the dust levels decreased below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing sheet piles in the CB slurry trench along the west alignment of the SOE wall.


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Spraying water and Biosolve for dust and odor control during excavation of the CB slurry trench.


Sounding the CB slurry trench to verify excavation to a depth of 48 feet below ground surface.


Applying odor suppressant foam to the CB slurry trench and surrounding area for odor control.


Excavating soil and installing the CB slurry trench along the west and north alignments of the SOE wall and applying odor suppressant foam to the excavated soil.



Update for the Week Ending July 8, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 9 trucks; 233.79 tons shipped last week; and
    • 7,606.14 tons shipped to date.
  • Continued installation of the sheet piles in the cement/bentonite (CB) slurry trench for the support of excavation (SOE) wall:
    • 27.6 linear feet installed last week; and
    • 629 of 629 linear feet installed.
  • Initiated installation of dewatering wells inside the SOE wall in preparation for the deep excavation.

Recently completed activities:

  • Completed excavation and installation of the CB slurry trench for installation of the SOE wall sheet piles; and
  • Obtained permitted access to the Bayside property along North 12th Street from NYC Parks and installed temporary fencing for equipment and supplies staging and storage.

Upcoming activities:

  • Complete installation of the sheet piles to the required depth for the SOE wall;
  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Initiate abandonment of monitoring wells located within the excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing sheet piles in the CB slurry trench along the north alignment of the SOE wall.


Installing dewatering wells inside the SOE wall and deep excavation area.


Installing dewatering wells and applying foam to the surrounding area and cuttings for odor control.


Breaking concrete foundations and applying water for dust control.


Installing temporary fencing on the North 12th Street Bayside property for equipment and supplies staging and storage.



Update for the Week Ending July 15, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 19 trucks; 496.09 tons shipped last week; and
    • 8,102.23 tons shipped to date.
  • Continued installation of dewatering wells inside the SOE wall in preparation for the deep excavation; and
  • Conducted shallow excavation and backfilled select fill with compaction on the east and west sides of the support of excavation (SOE) wall.

Recently completed activities:

  • Completed installation of the sheet piles in the cement/bentonite (CB) slurry trench to final depth for the support of excavation SOE wall:
    • 629 of 629 linear feet installed.

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Initiate abandonment of monitoring wells located within the excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing sheet piles in the CB slurry trench to final depth along the west alignment of the SOE walll.


Installing dewatering wells at the southeast corner inside the SOE wall and deep excavation area.


Installing dewatering wells inside the east alignment of the SOE wall and deep excavation area.


Conducting shallow excavation outside the east alignment of the SOE wall.


Conducting shallow excavation and loading trucks with soil for transfer to the impacted or reuse soil staging areas.


Backfilling the shallow excavation with select fill above the demarcation fabric.



Update for the Week Ending July 22, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads and excavated areas to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 33 trucks; 925.96 tons shipped last week; and
    • 9,028.19 tons shipped to date.
  • Continued crushing clean excavated material for reuse as backfill in the deep excavation;
  • Conducted shallow excavation and backfilled select fill with compaction on the east and west sides of the support of excavation (SOE) wall; and
  • Continued installation of dewatering wells inside the SOE wall in preparation for the deep excavation.

Recently completed activities:

  • Completed cutting the SOE wall sheet piles to grade in order to relocate the Temporary Containment Building (TCB) over the deep excavation area; and
  • Relocated the TCB from the southeast corner of the Site westward over the SOE wall in preparation for conducting the deep excavation.

Upcoming activities:

  • Expand the TCB northward over the SOE wall (from N. 11th Street to N. 12th Street) area in preparation for conducting the deep excavation;
  • Install the six vapor management system (VMS) units for the TCB;
  • Initiate abandonment of monitoring wells located within the excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing dewatering wells at the northeast corner inside the SOE wall and deep excavation area.


Cutting SOE wall sheet piles to grade.


Grading clean select fill with compaction in the shallow excavation areas.


Lined trucks entering the Site to be loaded with impacted soil for shipment to Bayshore Soil Management for treatment and disposal.


Compacting clean fill in preparation for moving the TCB.


Placing steel sheets beneath the base frame to assist with relocating the TCB.


Relocating the TCB over the SOE wall and deep excavation area.


Relocating the TCB over the SOE wall and deep excavation area.


Crushing clean material for reuse as backfill and applying water for dust control.


Covering the reuse soil stockpile with plastic for dust control.

 

Update for the Week Ending July 29, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads and excavated areas to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 22 trucks; 599.44 tons shipped last week; and
    • 9,627.63 tons shipped to date.
  • Continued crushing clean excavated material for reuse as backfill in the deep excavation;
  • Conducted shallow excavation and backfilled select fill with compaction on the east and west sides of the support of excavation (SOE) wall;
  • Initiated plumbing the ground water extraction wells and sumps to convey water from the deep excavation area to the WTP; and
  • Initiated the assembly of the expansion of the temporary containment building (TCB) over the deep excavation area.

Recently completed activities:

  • Completed installation of dewatering wells inside the SOE wall in preparation for the deep excavation.

Upcoming activities:

  • Install electrical service for the dewatering pumps and lighting for the TCB;
  • Install the six vapor management system (VMS) units for the TCB;
  • Initiate abandonment of monitoring wells located within the excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit on July 27, 2016, due to dust generated while breaking clean concrete in the shallow excavation.  Additional water was sprayed on the concrete, and the dust levels decreased to below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing a dewatering well on the eastern side of the SOE wall within the deep excavation area.


Installing piping from the ground water extraction wells to transfer water from the deep excavation to the WTP.


Conducting shallow excavation in the eastern areas of the Site.


Breaking clean concrete prior to crushing for reuse backfill in the deep excavation.


Offloading clean select fill for placement in the shallow excavation area.


Placing clean select fill in the shallow excavation areas.


Loading impacted soil in lined trucks for shipment to Bayshore Soil Management for treatment and disposal.


Expanding the TCB over the deep excavation area.


Cleaning the drill rig on the decontamination pad prior to demobilizing from the Site.



Update for the Week Ending August 5, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads and excavated areas to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 6 trucks; 173.66 tons shipped last week; and
    • 9,801.29 tons shipped to date.
  • Continued crushing clean excavated material for reuse as backfill in the deep excavation;
  • Loaded and transported two loads of clean asphalt to Bayshore Soil Management for recycling;
  • Continued shallow excavation and backfilled select fill with compaction on the eastern side of the Site;
  • Decommissioned four monitoring wells in the eastern areas of the Site;
  • Continued plumbing the ground water extraction wells and sumps with pumps to convey water from the deep excavation area to the WTP;
  • Continued the assembly of the expansion of the temporary containment building (TCB) over the deep excavation area; and
  • Initiated the installation of electrical service for the dewatering pumps and lighting and vapor management system (VMS) for the TCB.

Upcoming activities:

  • Install the six VMS units for the TCB; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Conducting shallow excavation in the eastern areas of the Site.


Loading clean excavated material for transfer to the reuse soil stockpile on Site.


Breaking the former holder tank sidewalls in the shallow excavation area.


Compacting the select fill in the shallow excavation areas.


Conducting compaction testing of the select fill.


Assembling the TCB superstructure (framework).


Lifting the superstructure with a crane to assemble the TCB.


Installing fabric on the TCB superstructure.



Update for the Week Ending August 12, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation in the eastern areas of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 33 trucks; 861.39 tons shipped last week; and
    • 10,662.68 tons shipped to date.
  • Continued crushing clean excavated material for reuse as backfill in the deep excavation;
  • Continued the placement and compaction of select fill in the shallow excavation areas:
    • 2,975.62 tons of select fill imported to the Site last week; and
    • 7,695.58 tons imported to date.
  • Continued the assembly the temporary containment building (TCB) components;
  • Continued the installation of electrical service for the vapor management system (VMS) for the TCB; and
  • Initiated installation of the VMS components for the TCB.

Recently completed activities:

  • Completed the installation of the TCB superstructure (frame and fabric) over the deep excavation area;
  • Completed electrical installation of the overhead lights in the TCB; and
  • Completed the installation and plumbing of the dewatering well pumps and initiated dewatering within deep excavation area.

Upcoming activities:

  • Complete installation, startup and testing of the six VMS units for the TCB; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There were three instances of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit:  On August 8 at AMS-2 due to dust created during breaking clean asphalt and concrete; on August 9 at AMS-2 due to dust created during compaction of clean backfill; and on August 11 at AMS-3 due to dust created during reuse material crushing activities.  When SES applied additional water, dust levels returned to below the Response Limit.  SES was directed to wet all areas down prior to initiating work that creates dust and throughout the duration of those activities.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing the superstructure (frame) for the TCB.


Installing air intake louvers for the VMS in the sidewall of the TCB.


Plumbing and installing electrical service to the dewatering well sumps in the deep excavation area.


Conducting shallow excavation in the eastern areas of the Site.


Breaking concrete in the shallow excavation area and applying water for dust control.


Loading excavated material from the shallow excavation area for transfer to the impacted soil staging area on Site.


Loading impacted soil from the staging area into lined trucks for shipment to Bayshore Soil Management for treatment and disposal.


Grading select fill lifts placed in the shallow excavation area.


Compacting select fill lifts placed in the shallow excavation area.


Crushing reuse material and applying water for dust control.


Applying long duration foam to the reuse soil stockpile for dust control.



Update for the Week Ending August 19, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued crushing clean excavated material for reuse as backfill in the deep excavation; and
  • Initiated the deep excavation within the support of excavation (SOE) wall under the temporary containment building (TCB).

Recently completed activities:

  • Completed the assembly the TCB components in new location
  • Completed the installation of electrical service for the vapor management system (VMS) for the TCB;
  • Completed the installation, startup and testing of the VMS components for the TCB; and
  • Properly abandoned one monitoring well located in the deep excavation area.

Upcoming activities:

  • Continue the deep excavation within the SOE wall; and
  • Continue the loading of lined trucks and shipment of impacted soils to Bayshore Soil Management for treatment and disposal.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing fabric doors on the TCB.


Installing VMS components for the TCB.


Loading carbon in the VMS filter beds.


Breaking hardscape (concrete and asphalt) prior to initiating excavation under the TCB.


Initiating excavation in the northeast corner under the TCB.


Applying water to the Site truck route for dust control.

 

Update for the Week Ending August 26, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued the deep excavation within the support of excavation (SOE) wall under the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 166 trucks; 4,315.06 tons shipped last week; and
    • 14,977.74 tons shipped to date.

Upcoming activities:

  • Initiate the installation of tie-backs through the SOE sheet pile sheet pile wall for external bracing.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing liners in the trucks prior to entering the Site.


Lined trucks entering the TCB to be loaded with impacted soils.


Loading lined trucks from the excavation at the north end of the TCB.


Excavating within the SOE sheet pile wall in the TCB.


Excavating and stockpiling impacted soils in the TCB.


Breaking concrete structures in the excavation.


Applying foam to the excavated material for VOC and odor control in the TCB.


Loading lined trucks with impacted soils in the TCB.


Pressure washing the lined and loaded trucks at the decontamination pad prior to leaving the Site.



Update for the Week Ending September 2, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued the deep excavation within the support of excavation (SOE) wall under the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 177 trucks; 4,901.17 tons shipped last week; and
    • 19,878.91 tons shipped to date.

Upcoming activities:

  • Initiate the installation of tie-backs through the SOE sheet pile sheet pile wall for external bracing; and
  • Continued shallow excavation and backfill on the western areas of the Site.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Conducting odor control at the WTP with an atomizer spraying water and BioSolve.


Lined trucks waiting to be loaded with impacted soils in the TCB.


Applying foam to the excavation for VOC and odor control in the TCB.


Applying BioSolve to the excavation for VOC and odor control in the TCB.


Removing a below-grade reinforced concrete tank from the deep excavation in the TCB.


Loading lined trucks with impacted soils in the TCB.


Closing the liner of loaded trucks prior to decontamination.


Cleaning trucks at the decontamination pad prior to leaving the Site.



Update for the Week Ending September 9, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued the deep excavation within the support of excavation (SOE) wall under the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 115 trucks; 3,024.61 tons shipped last week; and
    • 22,903.52 tons shipped to date.

Upcoming activities:

  • Initiate the installation of tie-backs through the SOE sheet pile sheet pile wall for external bracing;
  • Continued shallow excavation and backfill on the western areas of the Site; and
  • Continue crushing reuse material from the western shallow excavation.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Lined trucks waiting to be loaded with impacted soil in the TCB.


Excavating on the south end of the deep excavation in the TCB.


Excavating on the west side of the deep excavation in the TCB.


North end of the deep excavation and pumping from a sump located in the relief holder.


Cutting rebar for removal from subsurface concrete structures in the deep excavation.


Applying foam to the excavation for VOC and odor control in the TCB.


Loading lined trucks with impacted soils in the TCB.



Update for the Week Ending September 16, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued the deep excavation within the support of excavation (SOE) wall under the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 17 trucks; 490.46 tons shipped last week; and
    • 23,933.35 tons shipped to date.
  • Continued shallow excavation on the western areas of the Site;
  • Continued crushing reuse material from the western shallow excavation; and
  • Mobilized drill rigs and initiated the installation of tie-backs through the SOE sheet pile wall for external bracing.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the TCB; and
  • Continue backfilling with select fill in the shallow excavation.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit at AMS-2 on September 13, 2016 due to exhaust from an excavator operating near the station.

There were two instances of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit at AMS-3 on September 14, 2016 during shallow excavation while water was being applied.  Additional water was applied to the excavation, and the dust levels decreased below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Excavating impacted material in the deep excavation in the TCB.


Removing reinforcing steel from concrete structures in the deep excavation.


Placing a liner on the current bottom of the excavation in the TCB.


Placing clean stone on the liner for a work platform in the TCB.


Installing tie backs through the SOE sheet pile wall for external bracing to continue the deep excavation.


Breaking concrete structures to be removed in the shallow excavation and applying water for dust control.


Crushing reuse material and applying water for dust control.



Update for the Week Ending September 23, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued the deep excavation within the support of excavation (SOE) wall under the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 123 trucks; 3,520.23 tons shipped last week; and
    • 26,914.21 tons shipped to date.
  • Continued shallow excavation on the western areas of the Site;
  • Continued backfilling the shallow excavation with select fill and compacting; and
  • Continued the installation of tie-backs through the SOE sheet pile wall for external bracing:
    • 6 tie-backs installed last week; and
    • 6 of 76 tie-backs installed to date.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the TCB.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

There was one instance of the fifteen-minute average concentration of Particulate Matter (PM-10) [dust] exceeding the applicable Action Limit at AMS-3 on September 20 2016 during the breaking of clean concrete while water was being applied.  Additional water was applied to the excavation, and the dust levels decreased below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Removing concrete footers from the shallow excavation area.


Breaking clean concrete in the shallow excavation area.


Applying foam to the shallow excavation for VOC and odor control.


Loading lined trucks with impacted soil from the shallow excavation.


Installing demarcation fabric in the shallow excavation area prior to backfilling.


Washing the lined and loaded trucks at the decontamination pad prior to exiting the Site.


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation.



Update for the Week Ending September 30, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation on the western areas of the Site;
  • Continued backfilling and compacting select fill in the shallow excavation in the western areas of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 49 trucks; 1,404.36 tons shipped last week; and
    • 28,318.57 tons shipped to date.
  • Continued the installation of tie-backs through the SOE sheet pile wall for external bracing:
    • 7 tie-backs installed last week; and
    • 13 of 76 tie-backs installed to date.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the TCB; and
  • Initiate testing of the tie-backs.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (south wall).


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (east wall).


Backing lined trucks onto the Site to load impacted soil from the shallow excavation.


Excavating and breaking subsurface concrete structures in the shallow excavation.


Breaking subsurface concrete structures in the shallow excavation and applying water for dust control.


Applying foam to the shallow excavation for VOC and odor control.


Grading select fill in the shallow excavation area.


Grading and compacting select fill in the shallow excavation area.


Conducting compaction testing of the select fill lifts in the shallow excavation area.



Update for the Week Ending October 7, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water, odor-suppressant foam, and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation on the western areas of the Site;
  • Continued backfilling and compacting select fill in the shallow excavation in the western areas of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 55 trucks; 1,559.89 tons shipped last week; and
    • 29,878.46 tons shipped to date.
  • Continued the installation of tie-backs through the SOE sheet pile wall for external bracing:
    • 11 tie-backs installed last week; and
    • 24 of 76 tie-backs installed to date.
  • Initiated testing of the installed tie-backs.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the TCB.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for or odors during this reporting period.

There was an action level exceedance for Particulate Matter (PM-10) [dust] on October 3, 2016 at AMS-1 during shallow excavation and breaking of subsurface concrete structures while water was being applied to the excavation.  Additional water was applied, and PM levels dropped below the response limit.

There was an action level exceedance for Total Volatile Organic Compounds (TVOC) on October 3, 2016 at AMS-2 during fueling operations (diesel and gasoline) for heavy equipment and pressure washers.  Once fueling was completed, TVOC levels dropped below the response limit.

There were two action level exceedances for PM-10 on October 6, 2016 at AMS-2 during rock crushing operations.  SES applied additional water, and dust levels returned to below the response limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (south wall).


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (east wall).


Load testing installed tie-backs on the western SOE wall.


Loading clean reuse material from the shallow excavation for transfer to the crushing operation on the eastern area of the Site.


Breaking concrete to be crushed for reuse material and applying water for dust control.


Crushing reuse material on the eastern area of the Site and applying water for dust control.


Excavating impacted material in the shallow excavation.


Excavating impacted material and applying water for dust control.


Applying foam to the shallow excavation for VOC and odor control.


Grading select fill in the shallow excavation area.



Update for the Week Ending October 14, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for  Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation on the western areas of the Site;
  • Continued importing, backfilling, and compacting select fill in the shallow excavation in the western areas of the Site;
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 8 trucks; 184.79 tons shipped last week; and
    • 30,063.25 tons shipped to date.
  • Continued the installation of tie-backs through the support of excavation (SOE) sheet pile wall for external bracing:
    • 12 tie-backs installed last week; and
    • 36 of 76 tie-backs installed to date.
  • Continued testing of the installed tie-backs.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the temporary containment building (TCB).

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (east wall).


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (east wall).


Loading lined trucks with impacted soils from the shallow excavation for shipment to Bayshore Soil Management for treatment and disposal.


Grading select fill backfill in the shallow excavation area.


Compacting select fill backfill in the shallow excavation area.


Reinstalling the N. 11th Street decontamination pad.



Update for the Week Ending October 21, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation on the western areas of the Site;
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation;
  • Continued the installation of tiebacks through the support of excavation (SOE) sheet pile wall for external bracing:
    • 15 tie-backs installed last week; and
    • 51 of 76 tie-backs installed to date.
  • Continued testing of the installed tiebacks.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the temporary containment building (TCB); and
  • Continue lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC) or odors during this reporting period.

There were two action level exceedances for Particulate Matter (PM-10) [dust] on October 19, 2016 at AMS-2 during breaking and crushing of concrete reuse material and as reuse material was being offloaded from the Site truck to the eastern area of the Site while water was being applied to the area.  Additional water was applied in the vicinity of the truck offload area, and PM levels dropped below the response limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing (drilling) tiebacks (external bracing) for the SOE wall in the deep excavation (east wall).


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (west wall).


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (north wall).


Conducting shallow excavation in the western area of the Site.


Excavating and loading reuse material from the shallow excavation for transfer to the eastern area of the Site for crushing and stockpiling.


Breaking subsurface concrete structures in the shallow excavation area and applying water for dust control.


Washing the Site truck tires at the decontamination pad prior to exiting to N. 12th Street.



Update for the Week Ending October 28, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation;
  • Continued the installation of tiebacks through the support of excavation (SOE) sheet pile wall for external bracing:
    • 17 tiebacks installed last week; and
    • 68 of 75 tiebacks installed to date.
  • Continued testing of the installed tiebacks.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the temporary containment building (TCB);
  • Continue shallow excavation and backfilling on the western areas of the Site; and
  • Continue lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC) or odors during this reporting period.

There was one action level exceedance for Particulate Matter (PM-10) [dust] on October 24, 2016, at AMS-2 during breaking and crushing of concrete reuse material on the eastern area of the Site while water was being applied to the area.  Additional water was applied, and PM levels dropped below the response limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (west wall).


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (north and west walls).


Crushing reuse material on the eastern area of the Site.



Update for the Week Ending November 4, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation and backfilling on the western areas of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 59 trucks; 1,371.40 tons shipped last week; and
    • 31,434.65 tons shipped to date.
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation;
  • Continued the installation of tiebacks through the support of excavation (SOE) sheet pile wall for external bracing:
    • 7 tiebacks installed last week; and
    • 75 of 76 tiebacks installed to date.
  • Continued testing of the installed tiebacks.

Upcoming activities:

  • Continue deep excavation within the SOE wall under the temporary containment building (TCB).

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOC), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Winterizing and weatherproofing the water treatment plant components.


Installing (drilling) tie-backs (external bracing) for the SOE wall in the deep excavation (west wall).


Conducting shallow excavation in the western area of the Site.


Loading lined trucks with impacted soil from the shallow excavation area.


Applying foam to the shallow excavation area for VOC and odor control.


Grading select fill placed in the shallow excavation area.



Update for the Week Ending November 11, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation and backfilling on the western areas of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 68 trucks; 1,833.48 tons shipped last week; and
    • 33,268.13 tons shipped to date.
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation on the eastern area of the Site; and
  • Continued testing of the installed tiebacks.

Upcoming activities:

  • Continue the installation of tiebacks through the support of excavation (SOE) sheet pile wall for external bracing; and
  • Continue deep excavation within the SOE wall under the temporary containment building (TCB).

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOC), or odors during this reporting period.

There was one instance of the Particulate Matter (PM-10) [dust] levels exceeding the Action Limit at AMS-2 on November 9 at the eastern area of the Site.  No work was being performed in this area at the time, and dust levels quickly returned to below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Excavating non-impacted concrete structures for reuse from the shallow excavation area.


Loading reuse material from the shallow excavation area for transfer to the eastern area of the site for crushing.


Breaking subsurface concrete structures in the shallow excavation area and applying water for dust control.


Excavating impacted material from the shallow excavation area.


Breaking subsurface concrete structures in the shallow excavation area and applying water and foam for VOC and dust control.


Loading lined trucks with impacted soils from the shallow excavation area for shipment to Bayshore Soil Management for treatment and disposal.



Update for the Week Ending November 18, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation and backfilling on the western areas of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 131 trucks; 2,699.26 tons shipped last week; and
    • 35,967.39 tons shipped to date.
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation on the eastern area of the Site; and
  • Continued deep excavation within the SOE wall under the temporary containment building (TCB).

Recently Completed:

  • Completed the installation of tiebacks through the support of excavation (SOE) sheet pile wall for external bracing:
    • 1 tieback installed last week; and
    • 76 of 76 tiebacks installed.

Upcoming activities:

  • Complete the testing of the installed tiebacks.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOC), or odors during this reporting period.

There were three instances on Friday evening and Saturday morning, November 18 and 19, where benzene levels exceeded the Action Limit during nonworking hours.  Employees were called back to the Site to repair breaches and tears in the TCB fabric and to apply additional foam to the material stockpiled in the TCB.   Once these items were addressed, benzene and TVOC levels returned to below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Removing hardscape (asphalt and concrete) for reuse material from the shallow excavation area and applying water for dust control.


Excavating impacted soil in the shallow excavation area.


Offloading select fill for backfilling the shallow excavation area.


Installing (drilling) the last tieback through the northern SOE sheet pile wall.


Excavating impacted soil and installing (drilling) the tieback in the TCB.


Holder No. 1 tank uncovered in the south end of the deep excavation in the TCB.


Loading lined trucks with impacted soil from the deep excavation.


Lined trucks waiting to be loaded with impacted soil in the TCB.


Closing the liners of the loaded trucks prior to washing at the decontamination pad.


Washing the lined and loaded trucks at the decontamination pad prior to leaving the Site.

 

Update for the Week Ending November 25, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued shallow excavation and backfilling in the western area of the Site;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 107 trucks; 2,608.36 tons shipped last week; and
    • 38,616.89 tons shipped to date.
  • Continued deep excavation within the support of excavation (SOE) wall in the temporary containment building (TCB).

Upcoming activities:

  • Complete the load testing of the installed tiebacks for the SOE wall; and
  • Continued crushing and stockpiling reuse material to be used for backfill in the deep excavation on the eastern area of the Site.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], or odors during this reporting period.

There were multiple instances on Wednesday evening and Saturday morning, November 23 and 25, 2016, where benzene levels exceeded the Action Limit during nonworking hours.  Employees were called back to the Site to repair breaches and tears in the TCB fabric and to apply additional foam to the excavation in the TCB.   Once these items were addressed, benzene and TVOC levels returned to below the Response Limit.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Installing liners in the trucks prior to loading with impacted soils.


Breaking subsurface concrete structures in the western shallow excavation area.


Loading lined trucks with impacted soils from the western shallow excavation area.


Transferring select fill for backfilling in the shallow excavation.


Excavating in the deep excavation and applying BioSolve for VOC and odor control.


Excavating and breaking subsurface structures in the deep excavation.



Update for the Week Ending December 2, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued backfilling in the western shallow excavation area;
  • Continued deep excavation within the support of excavation (SOE) wall in the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 148 trucks; 2,608.36 tons shipped last week; and
    • 42,277.14 tons shipped to date.

Recently Completed:

  • Completed the load testing of the installed tiebacks for the SOE wall.

Upcoming activities:

  • Continue crushing and stockpiling reuse material on the eastern area of the Site to be used for backfill in the deep excavation.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOC), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Grading select fill backfill in the shallow excavation area.


Lined trucks waiting to be loaded inside the TCB.


Load testing tiebacks installed in the north SOE wall.


Excavating and stockpiling impacted soil in the TCB.


Excavating and applying Biosolve for VOC and odor control in the TCB.


Applying foam for VOC and odor control in the TCB.


Excavating and loading lined trucks in the TCB.


Applying foam and Biosolve for VOC and odor control in the TCB.



Update for the Week Ending December 9, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued deep excavation within the support of excavation (SOE) wall in the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 148 trucks; 2,608.36 tons shipped last week; and
    • 42,277.14 tons shipped to date.
  • Continued crushing and stockpiling reuse material on the eastern area of the Site to be used for backfill in the deep excavation.

Recently Completed:

  • Completed the load testing of the installed tiebacks for the SOE wall.

Upcoming activities:

  • Initiate backfilling the deep excavation with crushed and stockpiled reuse material; and
  • Complete excavation and backfilling in the western shallow excavation area.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOC), or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Crushing and stockpiling reuse material and applying water for dust control.


Excavating on the north end of the SOE wall and applying BioSolve for VOC control in the TCB.


Excavating on the south end of the SOE wall in the Holder No. 1 tank.


Excavating to install a dewatering sump in the northwest corner of the SOE wall.


Stockpiling excavated soil and applying foam for VOC and odor control.



Update for the Week Ending December 16, 2016

Site Remediation Continues

On-going activities:

  • Continued the application of water for dust control;
  • Continued the application of foam and BioSolve for Total Volatile Organic Compounds (TVOC), Particulate Matter (PM-10) [dust], and odor control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued pumping from the decontamination pads, excavated areas, sumps and dewatering wells to the water treatment plant (WTP);
  • Continued operation of the WTP and discharge to the sewer;
  • Continued deep excavation within the support of excavation (SOE) wall in the temporary containment building (TCB); and
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 182 trucks; 4,345.90 tons shipped last week; and
    • 48,276.37 tons shipped to date.

Recently Completed:

  • Completed crushing and stockpiling reuse material to be used for backfill in the deep excavation.

Upcoming activities:

  • Initiate backfilling the deep excavation with crushed and stockpiled reuse material; and
  • Complete excavation and backfilling in the western shallow excavation area.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOC), or odors during this reporting period.

The Action Limit for Particulate Matter (PM-10) [dust], was exceeded at AMS-3 on December 15, 2016 at multiple times throughout the day.  High winds were observed directing visible plumes of dust from the clean backfill areas towards the station. Calcium chloride was applied to the Site surface to suppress dust levels.

The Action Limit of 1.0 ppm for benzene was exceeded at AMS-3 on Saturday, December 18, 2016 from 6:49 to 6:51 am. During this time, no Site activity was taking place, and the winds were calm.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Crushing and stockpiling reuse material and applying water for dust control.


Guiding lined trucks into the TCB to load with impacted soils.


Excavating and stockpiling impacted soils and applying BioSolve for VOC control in the TCB.


Excavating and removing impacted soils from the SOE wall sheet piles.


Stockpiling and loading lined trucks with impacted soil in the TCB.


Washing the lined and loaded trucks at the decontamination pad prior to leaving the Site.