Site Remediation Continues
On-going activities:
- Continued the application of water and calcium chloride for dust control;
- Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
- Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
- Continued pumping from the decontamination pads and excavated areas to the water treatment plant (WTP);
- Continued operation of the WTP and discharge to the sewer;
- Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
- 33 trucks; 925.96 tons shipped last week; and
- 9,028.19 tons shipped to date.
- Continued crushing clean excavated material for reuse as backfill in the deep excavation;
- Conducted shallow excavation and backfilled select fill with compaction on the east and west sides of the support of excavation (SOE) wall; and
- Continued installation of dewatering wells inside the SOE wall in preparation for the deep excavation.
Recently completed activities:
- Completed cutting the SOE wall sheet piles to grade in order to relocate the Temporary Containment Building (TCB) over the deep excavation area; and
- Relocated the TCB from the southeast corner of the Site westward over the SOE wall in preparation for conducting the deep excavation.
Upcoming activities:
- Expand the TCB northward over the SOE wall (from N. 11th Street to N. 12th Street) area in preparation for conducting the deep excavation;
- Install the six vapor management system (VMS) units for the TCB;
- Initiate abandonment of monitoring wells located within the excavation; and
- Initiate the deep excavation within the SOE wall.
Community Air Monitoring Plan Summary
Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.
There were no fifteen-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOCs), Particulate Matter (PM-10) [dust], or odors during this reporting period.
If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.
Photos of Activity
Installing dewatering wells at the northeast corner inside the SOE wall and deep excavation area.
Cutting SOE wall sheet piles to grade.
Grading clean select fill with compaction in the shallow excavation areas.
Lined trucks entering the Site to be loaded with impacted soil for shipment to Bayshore Soil Management for treatment and disposal.
Compacting clean fill in preparation for moving the TCB.
Placing steel sheets beneath the base frame to assist with relocating the TCB.
Relocating the TCB over the SOE wall and deep excavation area.
Relocating the TCB over the SOE wall and deep excavation area.
Crushing clean material for reuse as backfill and applying water for dust control.