Williamsburg Works Interim Remedial Measure
NAPL Recovery Wells

The non-aqueous Phase Liquid (NAPL) Recovery Well installation and development field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of recovery wells to recover coal tar at the 50 Kent Avenue property of the Former Williamsburg Works MGP Site.

Activities Week April 14 – April 18, 2014

Prepared samples for analysis and characterization of liquid and soil for off-site disposal. Surveyed well locations.

Future (Two Week Look-Ahead) Activities

Off-site disposal of soil from roll-offs and liquid from storage tanks to appropriate disposal facilities. Demobilize all material and equipment from site.