Weekly Update April 4 2014
Williamsburg Works Interim Remedial Measure
NAPL Recovery Wells
Continued drilling at well locations on North 12th Street and onsite. Installed four (4) wells (NRW-05, NRW-06, NRW-07, and NRW-09) at these locations. Began developing wells on North 11th Street and onsite.
Activities Week March 31 – April 04, 2014
Commence with soft digging/pre-clearing of proposed well locations to 5 feet below ground both onsite and on North 11th Street.
Future (Two Week Look-Ahead) Activities
Complete drilling activities on North 12th Street. Complete well development and perform community air monitoring and PID screening.