Weekly Update March 28 2014
Williamsburg Works Interim Remedial Measure
NAPL Recovery Wells
The non-aqueous Phase Liquid (NAPL) Recovery Well installation and development field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of recovery wells to recover coal tar at the 50 Kent Avenue property of the Former Williamsburg Works MGP Site.
Activities Week March 24 – March 28, 2014
Continued drilling at well locations on North 12th Street and onsite. Installed five (5) wells (NRW-08, NRW-12, NRW-13, NRW-03, and NRW-04) at these locations.
Future (Two Week Look-Ahead) Activities
Continue drilling activities onsite and on North 12th Street. Begin well development and perform community air monitoring and PID screening.