The non-aqueous Phase Liquid (NAPL) Recovery Well installation and development field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of recovery wells to recover coal tar at the 50 Kent Avenue property of the Former Williamsburg Works MGP Site.

Activities Week March 3 – March 7, 2014

Commence with soft digging/pre-clearing of proposed well locations to 5 feet below ground both onsite and on North 11th Street.

Future (Two Week Look-Ahead) Activities

Continue soft dig/pre-clearing activities along North 12th Street and onsite for each proposed well location. Pre-Clear and expose inactive gas line in vicinity of NRW-07 on North 12th Street. . Mobilize drill equipment. Begin drilling activities concurrently with pre-clearing activities. Perform community air monitoring and PID screening.