Williamsburg Works Interim Remedial Measure

The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of April 23 – April 27, 2012

Completed groundwater level monitoring and permeability measurements. Initiated background noise and vibration measurements. Removed most of the investigation-derived waste and paved test pit holes. Performed general site cleanup.

Future (Two Week Look-Ahead) Activities

April 30 – May 4 – Remove last of soil generated during the investigation. Complete subsurface utility investigation

May 7 – May11 – No onsite activities planned.