Williamsburg Works Interim Remedial Measure
The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.
Activities Week of April 16 – April 20, 2012
Completed the installation and development of two wells. Performed testing on wells to gather data for estimating soil permeability.
Future (Two Week Look-Ahead) Activities
April 23 – April 27 – Perform groundwater level monitoring. Complete on-site activities. Perform background noise and vibration measurements.