Williamsburg Works Interim Remedial Measure

The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of April 9 – April 13, 2012

Completed the geotechnical soil borings. Began drilling the deep well location to set steel casing.

Future (Two Week Look-Ahead) Activities

April 16 – April 20 – Installation of an additional intermediate depth and a deep monitoring well.

April 23 – April 27 – Well development, slug testing, and groundwater level monitoring.