Williamsburg Works Interim Remedial Measure

The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of April 2 – April 6, 2012

Began installation of monitoring wells. One intermediate depth well was completed.

Future (Two Week Look-Ahead) Activities

April 9 – April 13 – Installation of an additional intermediate depth and a deep monitoring well.

April 16 – April 20 – Well development and groundwater level monitoring.