Williamsburg Works Interim Remedial Measure
The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.
Activities Week of March 26 - March 30, 2012
Completed drilling geotechnical borings and delineation borings.
Future (Two Week Look-Ahead) Activities
April 2 – April 6 – Installation of intermediate monitoring wells.
April 9 – April 13 – Installation of deep monitoring well and well development.