Remedial Investigation

Remedial Investigation field work at the former Williamsburg Works MGP is being conducted under a New York State Department of Environmental Conservation (NYSDEC)-approved Remedial Investigation Work Plan (RIWP).  The work includes the installation of soil borings, monitoring wells, and sediment cores to gather information required to determine the nature and extent of impacts at the former Williamsburg Works MGP. 

Based upon the findings of the field work completed to date, National Grid and NYSDEC agreed that additional off-site investigations were needed in the vicinity of the MGP.  The off-site work is described in the September 3, 2010 Supplemental RIWP which is available in the Key Documents/Major Reports section of this website.  The currently proposed Remedial Investigation field work was completed during December 2010.  National Grid is currently analyzing the collected data and evaluating additional activities.

Updating of this website will resume when field activities resume.