Update Week Ending, October 23, 2009

Remedial Investigation

Remedial Investigation field work commenced in early June at the former Williamsburg Works MGP as part of the New York State Department of Environmental Conservation (NYSDEC)-approved Remedial Investigation Work Plan (RIWP).  The work includes the installation of soil borings, monitoring wells, test pit excavations, sediment cores, and soil vapor points to gather information required to determine the nature and extent of impacts at the former Williamsburg Works MGP. 


Activities Week of October 19 – October 23:

  • There were no activities this week.

Future (two week look-ahead) activities:

  • Test pit installation activities will commence on October 26, 2009.
  • Groundwater sampling activities will commence on November 2, 2009.