July 2026

Operable Unit

Parcel ID

Block and Lot

Address

Site Proper

OU 1

Parcel 2

Block 2287, Lot 1

41 North 11th Street (aka 50 Kent Avenue)

Parcel 3

Block 2287, Lot 16

20 North 12th Street

Parcel 4

Block 2287, Lot 30

2 North 12th Street

OU 2

Parcel 1

Block 2288, Lot 1

35 Kent Avenue

Off-site

Not applicable

Parcel 5

Block 2294, Lot 1 and Lot 5

16 North 11 Street and 33 North 10th Street

Not applicable

Parcel 6

Block 2277, Lot 1

1 North 12th Street

Background:

National Grid is implementing a remedial program at the site.  To date, work has included the following:

  • A Remedial Investigation (RI) was performed by National Grid’s environmental consultant, GEI, from June 2009 through December 2012.
  • A Draft Remedial Investigation Report was submitted to NYSDEC in January 2015.
  • A NAPL recovery Interim Remedial Investigation (IRM) was conducted at Parcel 2 in 2014 and a Construction Completion Report (CCR) was approved by NYSDEC in 2015.
  • An excavation/stabilization-based IRM was performed at Parcel 2 from November 2015-June 2017 and the CCR for that effort was approved by NYSDEC in March 2018.
  • Remedial investigation work was performed on Parcels 3 and 4 from July through November 2022.
  • A revised Draft Remedial Investigation Report was submitted to NYSDEC on October 31, 2023.
  • Based on NYSDEC comments to the October 31, 2023 Draft Remedial Investigation Report, a Supplemental Remedial Investigation for Parcels 3 and 4 commenced in July 2024 and was completed in September 2024.
  • A revised Draft Remedial Investigation Report was submitted to NYSDEC on December 19, 2024.
  • A Revised Remedial Investigation Report was submitted to NYSDEC on July 17, 2025.
  • A Final Remedial Investigation Report was submitted to NYSDEC on August 29, 2025.
  • In September 2025, NYSDEC created operable units (OUs) 1 and 2 and approved the August 29, 2025 Remedial Investigation Report as the final Remedial Investigation Report for OU 1.

 

Highlights / Overall Update:

  • NAPL recovery at Parcel 2 has been ongoing since September 2014.
  • NAPL gauging and recovery at Parcel 3 and 4 since September 2022.
  • National Grid received a letter from Community Board No. 1 on June 17, 2026 that included a request for Committee Appearance.  National Grid responded to the letter on July 17, 2026
  • Draft Remedial Alternatives Analysis Report for OU 1 was submitted to NYSDEC on November 24, 2025.
    • National Grid has been engaging in open communications with NYSDEC and NYC Parks Department since the submittal of the draft Remedial Alternatives Analysis Report.
    • In July 2026,
      •  Worked to address NYSDEC requested modifications to the November 2025 draft OU 1 Remedial Alternatives Analysis Repor Conducted a call with the NYSDEC on July 9, 2026 to discuss the updated alternatives
      • Submitted the revised draft Remedial Alternatives Analysis Report to the NYSDEC on July 23, 2026

Recently completed actions/activities:

  • Submittal of revised draft Remedial Alternatives Analysis Report to the NYSDEC on July 23, 2026

On-going actions/activities:

  • OMM work, including:
    • Weekly NAPL gauging and recovery at Parcel 2, ongoing since September 2014.
    • Quarterly NAPL gauging and recovery at Parcels 3 and 4.
  • Outreach to Parks’ and NYSDEC counsel regarding fill wedge on Parcels 3 and 4
  • Maintain open communications with regulators and stakeholders.

Upcoming actions/activities:

  • Finalize draft Remedial Investigation work plan for Parcel 5 following receipt of NYSDEC draft investigation report, which is anticipated in July/August 2026.
  • Develop a draft Supplemental Remedial Investigation work plan for Parcel 6 following receipt of NYSDEC draft investigation report, which is anticipated in July/August 2026.
  • NYSDEC public meeting to discuss the NYSDEC Proposed Decision Document