June 2026
Designation of Operable Units
Approval of Remedial Investigation Report for Parcels 2, 3, and 4 (Operable Unit 1)
Submittal of Supplemental Remedial Investigation (SRI) Report for Parcel 6
Submittal of Operable Unit 1 Alternatives Analysis Reports
A map of the site and parcels can be seen on the Site Description tab. Individual parcel summaries can be found at:
Completed Activities:
- September 2025,
- NYSDEC created the following operable units. The approach and schedule for investigation and remediation will be specific for each OU:
- Operable Unit 1: Parcels 2, 3, and 4
- Operable Unit 2: Parcel 1
- NYSDEC approved the RI Report dated August 2025 for OU 1, and
- NYSDEC requested an Alternatives Analysis for OU 1.
- October 2025, National Grid submitted a Supplemental Remedial Investigation (SRI) Report for Parcel 6.
- November 2025, National Grid submitted the draft Remedial Alternatives Analysis Report for Operable Unit 1.
- April 2026, the NYSDEC provided comments on the draft Remedial Alternatives Analysis for Operable Unit 1
- May 2026, the NYSDEC requested additional supplemental remedial investigation activities on Parcel 6.
Ongoing Activities:
- Revisions to the Remedial Alternatives Analysis Report for Operable Unit 1.
- NAPL recovery
- Development of a Parcel 5 SRI Work Plan
- Development of a Parcel 6 SRI Work Plan
Upcoming Activities:
- Submittal of the revised Remedial Alternatives Analysis Report for Operable Unit 1
- Submittal of the Parcel 5 SRI Work Plan
- Submittal of the Parcel 6 SRI Work Plan