June 2026

Designation of Operable Units

Approval of Remedial Investigation Report for Parcels 2, 3, and 4 (Operable Unit 1)

Submittal of Supplemental Remedial Investigation (SRI) Report for Parcel 6

Submittal of Operable Unit 1 Alternatives Analysis Reports

A map of the site and parcels can be seen on the Site Description tab.  Individual parcel summaries can be found at:

Completed Activities:

  • September 2025,
    • NYSDEC created the following operable units. The approach and schedule for investigation and remediation will be specific for each OU:
      • Operable Unit 1: Parcels 2, 3, and 4
      • Operable Unit 2: Parcel 1
    • NYSDEC approved the RI Report dated August 2025 for OU 1, and
    • NYSDEC requested an Alternatives Analysis for OU 1.
  • October 2025, National Grid submitted a Supplemental Remedial Investigation (SRI) Report for Parcel 6.
  • November 2025, National Grid submitted the draft Remedial Alternatives Analysis Report for Operable Unit 1.
  • April 2026, the NYSDEC provided comments on the draft Remedial Alternatives Analysis for Operable Unit 1
  • May 2026, the NYSDEC requested additional supplemental remedial investigation activities on Parcel 6.

Ongoing Activities:

  • Revisions to the Remedial Alternatives Analysis Report for Operable Unit 1.
  • NAPL recovery
  • Development of a Parcel 5 SRI Work Plan
  • Development of a Parcel 6 SRI Work Plan

Upcoming Activities:

  • Submittal of the revised Remedial Alternatives Analysis Report for Operable Unit 1
  • Submittal of the Parcel 5 SRI Work Plan
  • Submittal of the Parcel 6 SRI Work Plan