Supplemental Remedial Investigation Commences

Supplemental Remedial Investigation (SRI)

Supplemental Remedial Investigation (SRI) field work was conducted at the former Williamsburg Works MGP site under a New York State Department of Environmental Conservation (NYSDEC) approved SRI Work Plan. The purpose of the work was to delineate vertical groundwater at Parcels 3 and 4 of the site.

The work consisted of installation and development of 16 monitoring wells on Parcels 3 and 4. The work was completed in September 2024. Information from the well monitoring was used to develop a draft revised Remedial Investigation Report, which National Grid submitted to NYSDEC in December 2024.

A map of the site and parcels can be seen on the Site Description tab.

Ongoing Activities:

  • Development of the Parcel 6 SRI Work Plan

Upcoming Activities:

  • Conduct Parcel 6 SRI, pending submittal and approval of Work Plan.