August 2024

Supplemental Remedial Investigation Commences

Supplemental Remedial Investigation (SRI)

Supplemental Remedial Investigation (SRI) field work will be conducted at the former Williamsburg Works MGP site under a New York State Department of Environmental Conservation (NYSDEC) approved SRI Work Plan. The purpose of the work is to delineate vertical groundwater at Parcels 3 and 4 of the site.

The work consists of installation and development of 16 monitoring wells on Parcels 3 and 4. The wells will then be left to equilibrate for two weeks prior to sampling. The work will begin in August and is expected to be completed by the end of September.

A map of the site and parcels can be seen on the Site Description tab.

Ongoing Activities:

  • Preparation for mobilization and fieldwork

Upcoming Activities:

  • Conduct approved Supplemental Remedial Investigation
  • Mobilization, installation of fencing, and pre-clearing activities will take place