Update for the Week Ending June 16, 2017

Site Restoration Underway

On-going activities:

  • Continued the replacement and installation of sidewalks on Kent Avenue, North 11th Street, and 12th Street; and
  • Continued the demobilization of electrical service equipment from support areas on North 12th Street.
Recently Completed:

  • Completed the decontamination and demobilization of equipment from the Site;
  • Completed the installation of sidewalks on Kent Avenue and North 11th Street;
  • Completed the import, placement, and grading of topsoil; and
  • Hydroseeded the Site.

Upcoming activities:

  • Complete the demobilization of electrical service equipment from the support areas on N. 12th Street;
  • Complete the replacement and installation of sidewalks on North 12th Street; and
  • Install permanent fencing and gates across N. 12th Street.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, was completed on May 31, 2107, with the completion of all intrusive activities on Site.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 982-7349.

Photos of Activity


Placing and grading topsoil.


Completing sidewalk installation on Kent Avenue.


Installing sidewalk on North 11th Street.


Completing sidewalk installation on North 11th Street.


Completing sidewalk installation on North 11th Street.


Hydroseeding the Site.


Aerial view of the hydroseeded Site.