Site Remediation Continues

On-going activities:

  • Continued the application of water and calcium chloride for dust control;
  • Continued the application of odor-suppressant foam and BioSolve for odor and dust control;
  • Maintained erosion and sediment (E&S) controls (Installed waddles - wood chip and straw filled fabric tubes - around the Site perimeter to prevent silt and sediment from leaving the Site and covered all stockpiles);
  • Continued operation of the water treatment plant (WTP) and discharge to the sewer;
  • Continued lining and loading trucks and shipping impacted soil to Bayshore Soil Management for treatment and disposal:
    • 15 trucks; 427.20 tons shipped last week; and
    • 4,452.05 tons shipped to date.
  • Continued excavation and installation of the cement/bentonite (CB) slurry trench for installation of the support of excavation (SOE) wall sheet piles:
  • None installed to final depth (48 feet below ground surface); and
  • 282 of 629 linear feet installed to date

Upcoming activities:

  • Relocate and expand the temporary containment building (TCB) over the SOE wall area in preparation for conducting the deep excavation;
  • Install deep wells for dewatering in preparation for conducting the deep excavation; and
  • Initiate the deep excavation within the SOE wall.

Community Air Monitoring Plan Summary

Community air monitoring, initiated on Tuesday, December 1, 2015, continues as intrusive (ground disturbance) activities are conducted.

There were no fifteen-minute Action Limit exceedances for Particulate Matter (PM-10) [dust], Total Volatile Organic Compounds (TVOCs) or odors during this reporting period.

If you have any questions or comments about the work on the Site, please use the Williamsburg MGP Telephone Hotline at (718) 403-3053.

Photos of Activity


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Excavating soil and installing the CB slurry trench along the west alignment of the SOE wall.


Loading CB slurry spoils for transfer to the lined containment area in the TCB.


Closing the truck liner prior to proceeding to the decontamination pad.


Offloading super sacks of bentonite at the grout plant using a plastic shroud and water to mitigate dust.