Weekly Update, Week Ended March 29, 2013 Williamsburg Works Interim Remedial Measure

The Supplemental Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the advancement of soil borings to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of March 25 – March 29, 2013

Performed hand clearing of planned soil boring locations.

Future (Two Week Look-Ahead) Activities

Advance soil borings to collect geotechnical data and visually log MGP materials.