Williamsburg Works Interim Remedial Measure

The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of March 19 - March 23, 2012

Completed drilling delineation borings. Completed test pits. Began drilling geotech borings.

Future (Two Week Look-Ahead) Activities

March 26 – March 30 - Drilling of geotech borings will continue. Installation of intermediate and deep monitoring wells will begin.

April 2 – April 6 – Completion of monitoring well installations and well development.