Williamsburg Works Interim Remedial Measure

The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of March 05 - 09, 2012

Continued drilling of delineation borings.

Future (Two Week Look-Ahead) Activities

  • March 12 – March 16 - Drilling of delineation borings will continue. If completed, drilling of geotechnical evaluation borings will begin. Test Pitting will start on March 15.
  • March 19 – March 23 – Completion of test pitting and geotechnical evaluation borings. Commence installation of monitoring wells.