Weekly Update, Week Ended February 17, 2012

Interim Remedial Measure

The Pre-Design Investigation field work for the 50 Kent Avenue Interim Remedial Measure (IRM) includes the installation of soil borings, monitoring wells, and test pits to gather information required to determine the design parameters of the interim remedial measure at the 50 Kent Avenue parcel of the Williamsburg Works MGP Site.

Activities Week of February 13 - 17

A site visit was conducted and investigation locations were marked out.

Future (Two Week Look-Ahead) Activities

The Pre-Design Investigation (PDI) field work for the 50 Kent Avenue Interim Remedial Measure (IRM) begin during the week of February 20 - 24, 2012 with a review of existing conditions at the property prior to start of PDI field work.

The PDI field work is scheduled to start on February 23, 2012 with pre-clearing of the locations where test borings will be installed. Starting with the week of February 27, 2012, The PDI consultant will install test borings to further delineate the extent of MGP contamination on the site.